Work under way at water treatment plant

Although the water treatment plant project will not finish until the end of the year, residents have been able to see clear signs of progress on the project in recent days.

Work on the $4 million state-mandated project will continue throughout the summer and into the fall before wrapping up in December.

Officials from Lamont engineers said once principal construction is complete on the water treatment plant and it comes online at the end of 2011, the only work remaining will be some cosmetic grounds keeping at the facility. 

“We’re excited about work getting started down there,” Mayor Brian LaRose said. Although the project is one Granville was required to rather than started by choice, LaRose said in the long run the village will be better off for it with a new water system and new infrastructure to distribute it.

The village department of public works kept busy last week hopping from repair job to repair job as work began on the project.

“This is one of the things we were worried about when we started this project,” public works superintendent Dan Williams said. “Some of these valves haven’t been touched in (many) years and when we do, they break.”

Williams said village workers replaced three valves in 24 hours as they worked to shut off the water to allow workers from the Gansevoort-based Tom Kubricky Co. Inc. to replace water mains in the Columbus Street area. The pace the Kubricky crew was taking impressed Williams, who added things had been going smoothly since the water main replacement work started.

Upgrades to the water distribution system include replacing water mains in the area of Columbus and Mettowee streets.

Workers from Kubricky Company worked during the week placing mains from Williams Street across Columbus Street towards Mettowee Street. The work will end before Mettowee Street crosses the bridge to Route 22, Williams said.

At the site of the eventual water treatment plant, adjacent the carnival grounds off of Park Avenue, workers with Riznick Construction Inc. prepared the site for pouring concrete for the building’s foundation.

Lamont Engineers Jason Prizer said ‘substantial’ completion of the water plant was not expected until December, but the project’s early work looked to be proceeding as scheduled.

“It’s going good,” he said. 

Workers from Parker Water Works of East Poultney, Vt. continued working on the four large wells which will feed the water system.

Oakley Allen, a technician for the company from Middletown Spring, Vt. said the crew had one well to finish and one more left to work on.

The company attached well heads to the wells previously drilled in anticipation of the water treatment project; later they will return to place the submerged pumps which will move the water out of the ground, an upgrade from the suction system currently in place.

Despite the cost of the project, village officials have said they expect to be able to keep users from experiencing large swings in the water rates.  

Village Clerk Rick Roberts said the water rates this year will increase from $135 per year to $150.

Officials said the anticipate over the next three to four years rates going up to about $180 to $195 per year. “We see it stepping up over time,” Roberts said.

 

 

Comments

comments

Read more in this week's Sentinel in newsstands now or click here to read right now with our e-edition.

Tags: , , , , , , , , , , ,

Weekender – 08/28/15

Lakes Classifieds – 08/28/15

Lakes Region Freepress – 08/28/15

Northshire Freepress – 08/28/15

Classifieds 08/27/15

Washington County Fair in full swing

407624_345593242132090_322483287_n

By Linda Ellingsworth There’s still plenty of time to experience the excitement of the Washington County Fair. A celebration of […]

Coin drops hurt by bridge work

Bridge

By Dan King Those who volunteer their time to serve the people of Whitehall say their coin drop operations have […]

Working together: town, village fixing waterline

DSC_1921

By Dan King For the past week and a half the town and village of Whitehall have been working together […]

Washington County Board opposes Common Core

Schulz 2

By Dan King The third time was indeed a charm for Hartford Supervisor Dana Haff and activist Bob Schulz. Haff […]

Townwide sale next weekend

Lawn sale 006

By Dan King Bargain seekers will converge on Whitehall Labor Day Weekend, as they seek the best deals around. The […]

Three vying for public safety position

By Christina Scanlon Washington County supervisors have narrowed the field to three candidates for county public safety director and will […]

Recycled teens applauded

By Christina Scanlon Nine honorary members of the Mettowee Valley Senior Citizens were honored last week at a luncheon filled […]