Auditorium roof work starts early

T he first phase of a two-phase construction project that will result in the complete renovation of theWhitehall Jr.Sr.High Schoolauditorium began earlier this week, a couple weeks earlier than expected.

Superintendent James Watson said at Monday’s monthly Board of Education meeting crews came in over the weekend and began the process of removing and renovating the existing roof.

Crews worked for a period of time Sunday evening and Monday before taking a break to allow Tuesday’s wet weather to pass. They returned to work on Wednesday.

Watson said he was told the work should take about five days of clear weather to complete.

Workers had already completed the removal and abatement of asbestos that was in the old roof. 

The work was scheduled to begin on Oct. 1 but crews were able to begin nearly two weeks before the date.

The second phase of the project, the renovation of the auditorium is expected to begin later this winter, probably sometime in February.  

The renovation will include the replacement of seating, staging, carpeting, rigging and lighting, painting and repairs, and upgrades to the existing sound system.

Although the second phase of the project is expected to disrupt some programs, notably the annual drama production (which is expected to be held several months earlier in January as a result) the first phase had had little impact on students thus far.

Programs were still being held in the auditorium as of Monday evening.

Voters approved both phases of the project during a June 29 vote. A ballot item to replace the roof passed 65-3 while the renovation of the auditorium was approved 57-5.

The total cost of the project has been estimated at $625,000. That sum includes $115,000 for the roof and $510,000 for the second phase of the project.

The project is being paid for by a transfer of monies from the General Fund to the Capital Project account and a “future renovations to the Elementary and Jr./Sr. high school buildings capital reserve fund.

Administrators have contended that the project will not affect taxes.

In other matters, Budget Officer Jodi Bradshaw said an audit of the district’s finances was completed and the school received an A+ rating.

She said 2008 was the last time an audit was completed and the district received the same A+ rating at the time.

Comments

comments

Read more in this week's Times in newsstands now or click here to read right now with our e-edition.

Tags: , , , , , , , , , , , , , , , , , , ,

Northshire Freepress – 07/31/15

Lakes Classifieds – 07/31/15

Lakes Region Freepress – 07/31/15

Weekender – 07/31/15

Classifieds 07/29/15

Rain stops, the park rocks

Magill and Macri 3 cover

By Jamie Norton The skies opened up five minutes before Daryl Magill – one of the biggest draws of the […]

Dresden works to eradicate invasive weeds

Water chestnut harvester redit VT DEC

By Dan King The town of Dresden has started its annual effort to remove invasive water chestnuts from Lake Champlain, […]

Man walking to D.C. to ‘raise awareness’

don

By Dan King Don Duncan may be 65 years old but he’s not letting that stop him from raising awareness […]

Town, village to pledge support for bike trail

Canal Trail

By Dan King A multi-use trail from Waterford to Whitehall is expected to receive letters of support from both the […]

Hebron woman charged with urinating outside store

By Christina Scanlon A Hebron woman faces several charges, including driving while intoxicated and possession of marijuana, after witnesses and […]

Area man to hold talk about Robin Williams

By Linda Ellingsworth It’s been almost a year since the untimely passing of comic great Robin Williams, and a local […]

Ride to benefit veterans

By Christina Scanlon When the bikers hit the road for the third annual ride to benefit the Wounded Warrior Project […]