Village asks firm to study power line

 

The village has asked an engineering firm to study the possible impact a power line stretching from Canada to New York City could have on its water system.

The Champlain Hudson Power Express, a proposed 333-mile power line stretching from Canada to New York City, would see two five-inch thick cables run south under the waters of Lake Champlain and along the east side of Route 22 before meeting the Canadian Pacific Railway tracks and continuing to a converter station in Astoria.

The proposed route runs along the same path where the village plans to install a new water main this fall.

“It’s potentially a problem,” said Mayor Peter Telisky.

He has asked Barton and Loguidice engineers to contact Transmission Developers Inc., the company behind the project, to discuss it. Contrary to published reports, Barton and Loguidice have not been hired explicitly to study the project.

“They were hired to do the water line and my position is this (the study) is part of the job,” Telisky said. “There needs to be a dialogue.”

Transmission Developers, Inc., was required to provide $450,000 to the state to fund expenses incurred by municipalities related to the project and Telisky is hopeful some of that money may be available to pay for any study.

The village plans to install the water main north of the village and south of South Bay near the county highway garage.

The work is a continuation of the same project that saw several thousand feet of water main replaced on Broadway last year.

Telisky said the stretch of water line that’s to be replaced was chosen because of the number and severity of leaks that have occurred. “We felt it should take precedence,” he said.

Most of the pre-engineering work on the water line has already been done and officials expect the project to begin in October and wrap up next spring.

According to Donnie Williams, director of public works, the power line would follow the water main from Blue Goose Road all the way to Clinton Avenue.

Officials fear the power line could become problematic if the village needs to access and repair its water main in the future. They have questioned whether the power line could run through South Bay along the railway instead.

Developers hope to begin construction of the electric project in 2014, but there is still engineering work to be done and construction plans along parts of the route still need to be completed and submitted to the state.

The project isn’t expected to be complete until 2016.

When it’s finished, the project is expected to bring up to 1,000 megawatts of wind and hydro power to the New York metropolitan area. Developers have said it will create hundreds of jobs, meet growing energy demands, reduce emissions and lower energy costs for consumers.

The town and village could potentially receive additional tax revenue because the power line would represent an improvement, thus increasing the taxable value of the land. Approximately six miles would pass through Whitehall; two through the village and four through the town.

The project’s cost equates to more than $6 million per mile and developers estimate it will generate more than $20 million in taxable revenue where the line is buried.

In addition, a one-time payment will be made to the state for easements once the project is complete.

Developers still need approval from the Public Service Commission, the U.S. Department of Energy and the Army Corps of Engineers before construction can begin.

 

Comments

comments

Read more in this week's Sentinel in newsstands now or click here to read right now with our e-edition.

Read more in this week's Times in newsstands now or click here to read right now with our e-edition.

Tags: , , , , , , , , , , , , ,

Weekender – 08/28/15

Lakes Classifieds – 08/28/15

Lakes Region Freepress – 08/28/15

Northshire Freepress – 08/28/15

Classifieds 08/27/15

Washington County Fair in full swing

407624_345593242132090_322483287_n

By Linda Ellingsworth There’s still plenty of time to experience the excitement of the Washington County Fair. A celebration of […]

Coin drops hurt by bridge work

Bridge

By Dan King Those who volunteer their time to serve the people of Whitehall say their coin drop operations have […]

Working together: town, village fixing waterline

DSC_1921

By Dan King For the past week and a half the town and village of Whitehall have been working together […]

Washington County Board opposes Common Core

Schulz 2

By Dan King The third time was indeed a charm for Hartford Supervisor Dana Haff and activist Bob Schulz. Haff […]

Townwide sale next weekend

Lawn sale 006

By Dan King Bargain seekers will converge on Whitehall Labor Day Weekend, as they seek the best deals around. The […]

Three vying for public safety position

By Christina Scanlon Washington County supervisors have narrowed the field to three candidates for county public safety director and will […]

Recycled teens applauded

By Christina Scanlon Nine honorary members of the Mettowee Valley Senior Citizens were honored last week at a luncheon filled […]